Sterk - Hoogwaterkering IJmuiden

Flood Barrier IJmuiden

Description

Published: December 13th, 2017

The new sea lock being constructed in IJmuiden is an extraordinary project. Rijkswaterstaat, the national agency responsible for public works and water management in the Netherlands, awarded the contract for its construction to the OpenIJ consortium. With a length of 500 metres and a width of 70 metres, it will be the largest sea lock in the world.

In early 2017, Sterk installed sheet piling for a temporary landing wharf, but the real work only started this autumn! For a temporary flood barrier we had to install piles of no less than 27 metres in length. To make it even more challenging, these piles had to be put in place with our Silent Piler using the ‘press-in’ technique – and all this at 7 metres above sea level. This meant that, depending on the tide, the press-in machine would be suspended at between 6 and 8 metres above the water.

The first piles were installed using a starting frame. This frame was loaded with several tons of ballast so that the machine had sufficient power to press the piles into the ground. After the first piles had been put into place, the Silent Piler could be clamped onto the piles already in position and continue its work.

And as if that weren’t complex enough, there was more to come. The sheet piling also had to be lengthened. In other words, the sheet piles already in place had to be extended by welding on an extra piece of sheet piling. And all this had to be done in line with execution class III under the EN 1090 standard. Without special measures in situ it would not have been possible to meet these stringent welding requirements. For that reason, for this job, Sterk Metaal produced a special welding container which could be positioned on the sheet piling. In this way it was possible to work under the proper conditions.

Project details

  • Contractor: OpenIJ
  • Location: IJmuiden (NL)
  • Contract value: € 250.000 - 1.000.000
  • Start date: August 2017
  • End date: November 2017

Techniques used

(Pre-)drilling, Construction work, Fluidisation, High-frequency vibration/extraction, In-water work, Specialist techniques, Static driving

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

OpenIJ

Locatie

IJmuiden (NL)

Contractwaarde

€ 250.000 - 1.000.000

Start datum

August 2017

Eind datum

November 2017

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Sterk - hoogwaterkering Brunsbüttel

Flood Protection Brunsbüttel (DE)

Description

Posted on October 9th, 2017

Brunsbüttel (about two and a half hours’ drive in a north-easterly direction from Bremerhaven) is situated on the River Elbe. For some time now, work has been carried on new lock infrastructure there. The construction of a 360-metre-long fifth lock at the entrance to the Kiel Canal on the Elbe is essential for the renovation of the 100-year-old complex of locks and to increase capacity. The entrance to the lock approach on the Elbe side is also being modified. Around 120 vessels a day negotiate these locks.

As part of this large-scale project, Sterk had the task of installing sheet-piling for temporary flood protection. To do this, the section closest to the old lock head was installed by silent piling using the ‘press-in’ technique.

This concerned 40 metres or so of sheet piling of the type AZ38-700, in lengths of 16 metres. The other 80 metres of piling, of type ZZ17-700, was applied with the KH-125 using a vibration method. Steel tie rods were also put in place adjacent to the construction road being built. The section connecting the old lock head was installed using Larssen 604 sections, welded at right angles, which were pressed into place and later injected.

One challenging aspect of the operation was the logistics. The new location is situated between the two older locks and, as such, can only be accessed by ferry (specially purchased for this project by the construction consortium). The cranes had to be likewise transported to the site using the ferry. From there it was possible to work from land.

The work was commissioned by ARGE Neubau 5. Schleusenkammer Brunsbüttel comprising BAM and Wayss & Freytag, a German subsidiary of BAM.

Project details

  • Contractorr: Arge Neubau
  • Location: Brunsbüttel (DE)
  • Contract value: € 250.000 - 1.000.000
  • Start date: 15-08-2017
  • End date: 01-11-2017

Techniques used

Anchoring constructions, Construction work, High-frequency vibration/extraction, Static driving
Sterk - Waterkering Brunsbüttel

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Arge Neubau

Locatie

Brunsbüttel (DE)

Contractwaarde

€ 250.000 - 1.000.000

Start datum

15-08-2017

Eind datum

01-11-2017

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Wilhelmshaven Duitsland

Amphibian Slope Wilhelms Harbour Germany

Description

The deconstruction of an amphibian slope in Wilhemshaven in Germany was the type of specialist job that was tailor-made for our colleagues at Sterk Spezialtiefbau. From a corner of the harbour we removed three slopes that up until recently were used by the German navy to launch amphibian vehicles in the water. Because of a lack of space in the harbour it was decided that these needed to be removed.

To be able to execute the demolition work, two temporary sheet-pile screens were installed. These separated the section that needed to be removed from the existing quay. This allowed the demolition work such as the removal of the top layer of basalt, stairs, old sheet piling and anchoring to be carried out. The construction site is approximately 1800 m2 and more than 2500 m3 of soil needed to be removed and transported away. In addition around 3300 m of anchoring, 250 m2 of concrete stairs and bollard foundations, 46 foundation piles, and about 2500m2 of sheet piling was removed.

It was important that all work was done in dry conditions. Because of the tides, the difference between the lowest excavation point and the highest water level could be as much as 6 m. It was also important to make sure that the soil was free of debris, because at a later stage, after the temporary sheet piling had been removed, the site was going to be dredged down to minus 10 metres.

Project details

  • Client: Strabag Wasserbau GmbH
  • Location: Wilhelmshaven - Germany
  • Contract value: € 250.000 - 1000.000
  • Start date: 18-01-2016
  • End date: 04-05-2016

Used techniques

High-frequency vibration/extraction, Removal of foundation piles, Specialist techniques, Underwater demolition work
Wilhelmshaven Duitsland

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Strabag Wasserbau GmbH

Locatie

Wilhelmshaven - Germany

Contractwaarde

€ 250.000 - 1000.000

Start datum

18-01-2016

Eind datum

04-05-2016

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Combiwand Baakenhafen Duitsland

Baakenhafen city renewal project

Description

Sterk Spezialtiefbau continues to work on extraordinary and specialist jobs. Last year we made a large construction pit for the extensive ‘Baakenhafen’ city renewal project. The structure was made up of a combined wall consisting of both tubular piles and sheet piles that was installed completely vibration-free. It consisted of approximately 160 metres of combined wall for the construction of a parking garage and its two associated buildings.

Both the tubular piles (with a length of 18 metres) as well as the sheet piles were installed with the recently acquired Woltman using two different techniques: the tubular piles were rotated into the ground while the sheet piles were pressed in.

But not only was the installation of the combined wall unusual. The accompanying ‘bracing frame’ was also rather uncommon because the use an adjacent wall to create a bracing frame was not possible due to the location.

Therefore an alternative construction was required. The decision was made to combine horizontal braces (made up of tubular piles) with vertical elements. These were then held into place by grout anchors: two for each brace.

The other half of the construction will be made in a different way and at a later stage. Part of the building will be constructed first so that the bracing frame can installed on the basement deck.

Project details

  • Client: Arge Jacob August Ernst
  • Location: Baakenhafen Germany
  • Contract value: € 250.000 - 1000.000
  • Start date: 28-05-2015
  • End date: 01-08-2016

Used techniques

Anchoring constructions, Combi sheet pile walls, Construction work, Static driving, Static extraction, Strutting
Combiwand Backenhafen Duitsland

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Arge Jacob August Ernst

Locatie

Baakenhafen Germany

Contractwaarde

€ 250.000 - 1000.000

Start datum

28-05-2015

Eind datum

01-08-2016

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Parking Garage “Jaarbeursplein”

Description

At the Jaarbeurs (Convention Centre) square in Utrecht Sterk has installed the steel sheet piles for the construction of a large underground parking garage. A substantial job at one of the busiest areas in the Netherlands.

The sheet piles with a length of almost 20 m were nearly all statically pressed into the ground. Because of the soil conditions the last few metres of the sheet piling had to be installed with a high frequency vibratory hammer. This was done during specially assigned time slots in order to reduce nuisance to a minimum.

The outline of the sheet pile area was pre-augered in order to reduce soil resistance. At the same time bentonite was inserted to prevent the soil from compacting.

Sterk will also be installing the sheet piling for the parking garage entrance. In this case a bracing frame was added for support.

The square is undergoing a great metamorphosis. The plan is that the square will become a place where people can meet, but will also serve as a venue for major events.

Completion of the parking garage is planned for 2018. It will have room for approximately 800 cars.

Project details

  • Client: Combination Jaarbeurs Square
  • Location: Utrecht
  • Contract value: € 250.000 - 1000.000
  • Start date: 15-01-2016
  • End date: 02-02-2017

Used techniques

(Pre-)drilling, High-frequency vibration/extraction, Static driving, Static extraction, Strutting

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Combination Jaarbeurs Square

Locatie

Utrecht

Contractwaarde

€ 250.000 - 1000.000

Start datum

15-01-2016

Eind datum

02-02-2017

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

VUmc Imaging Center

Description

Sterk has made a proud contribution to the construction of the VUmc Imaging Center. This building will house the latest medical imaging technology under one roof which will make it unique in the world! With the help of the newest imaging techniques treatment can be tailored even better to a patient’s unique needs.

This extraordinary building must meet a number of strict requirements. It must be vibration-free and must meet many safety regulations in areas such as radiation safety and pharmaceutical safety while it is also essential that the different devices do not interfere with each other’s functioning/operations.

The new building is being constructed in the garden next to the existing clinic. Sterk installed the sheet-piling of the 155 by 60 metres’ pit for a double-level parking garage. Part of the sheet-piling wall closest to the existing building was pressed into the soil in order to prevent harmful vibrations. The rest was installed by vibratory means.

Most of the sheet-piling wall is temporary, although a small section of it will remain in the soil permanently as it is not possible for it to be removed once further construction on the building has started.

A major part of the construction was anchored with 80 grout anchors approximately 28 metres in length.

Because of the type of work that will take place inside the new building (involving radiation or the storage of medical products) some parts of the concrete wall will be more than 1.5 metres thick.

Completion of the building is planned for 2020.

Project details

  • Client: Ballast Nedam Bouw & Ontwikkeling Speciale Projecten Nederland bv
  • Location: Amsterdam
  • Contract value: € 250.000 - 1000.000
  • Start date: 04-04-2016
  • End date: 20-05-2016

Used techniques

(Pre-)drilling, Anchoring constructions, High-frequency vibration/extraction, Static driving, Static extraction

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Ballast Nedam Bouw & Ontwikkeling Speciale Projecten Nederland bv

Locatie

Amsterdam

Contractwaarde

€ 250.000 - 1000.000

Start datum

04-04-2016

Eind datum

20-05-2016

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Wildlands Adventure Zoo

Description

For the expansion of the zoo in Emmen the Netherlands, Sterk has completed several different activities for its contractors KWS and Koenen Bouw. We installed sheet piling for the build of the “Polestation” (the residence of the polar bears) and the basin of the fur seals.

For the Polestation we installed 112 metres of sheet piling of the type AZ12-770 with a length varying from 5.00 to 9.25 metres. The largest part of this construction has been coated mainly for esthetic reasons. This was done on location. To keep the sheet piling stable, anchoring was put into place as well. Two different types of ground anchors were used. The most remarkable thing about this anchoring construction was that the attachment structure of the anchors to the sheet piles was placed at the back of the sheet piling instead of the front because people thought that otherwise the polar bears would be able to climb out of their stay by using this construction as a step. Our structural engineer came op with a unique solution that allowed for the anchoring to be attached to the back of the sheet piles.

For the seal basin we installed about 277 metres of sheet piling in varying lengths. Normally our clients wish the sheet piles to all be placed at the same height. With this project however certain parts were (supervised by the architect) installed at different heights to create a more playful effect. This sheet-piling construction also utilized anchoring be it that this time the regular (front-side facing) anchor chairs could be used.

Both basins will be made watertight by applying foil witch was attached to the sheet piles using a special construction. Lastly, all locks of the sheet piles were welded shut from the top all the way to the protective foil layer. The last of Sterk’s activities for this great project were finished by the end of March.

Project details

  • Client: KWS en Koenen Bouw
  • Location: Emmen
  • Contract value: € 250.000 - 1.000.000
  • Start date: 06-10-2014
  • End date: 27-03-2015

Used techniques

Anchoring constructions, Construction work, Design en construct, High-frequency vibration/extraction, Strutting

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

KWS en Koenen Bouw

Locatie

Emmen

Contractwaarde

€ 250.000 - 1.000.000

Start datum

06-10-2014

Eind datum

27-03-2015

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Oudenbosch Underpass

Description

In September 2014 Sterk was responsible for quite a feat of foundation work. In a single day Sterk installed the box piles and sheet pile planks for a carrier construction of a new tunnel deck. Sterk used four cranes in order to meet this extremely short deadline.

In Oudenbosch the Netherlands a new bypass is being built that will greatly improve traffic flow. Part of this bypass is a railroad underpass. In the weekend of September 13th the large tunnel deck of this underpass was put into place.

Installation of the deck meant interrupting train traffic. Whereas normally this type of work is done in two separate phases, it was decided that this time all the work had to be completed in a single phase so that train passengers would undergo as little nuisance as possible.

This meant that in a single weekend the track had to be broken down, groundwork had to be done, the carrier construction had to be installed and the tunnel deck had to be put into place. After all of this the track could be reassembled.

Hard work, solid preparation and good communication between all parties involved made it possible that the railway was closed on Friday night but was back in use on Monday morning.

Project details

  • Client: Strabag
  • Location: Oudenbosch
  • Contract value: € 250.000 - 1.000.000
  • Start date: 13-09-2014
  • End date: 14-06-2015

Used techniques

Combi sheet pile walls, Fluidisation, High-frequency vibration/extraction

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Strabag

Locatie

Oudenbosch

Contractwaarde

€ 250.000 - 1.000.000

Start datum

13-09-2014

Eind datum

14-06-2015

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Underground Parking Garage Deventer Station

Description

In May 2014 Sterk started with placing the sheet-piling construction for the foundation pit of what will become an underground bicycle garage at Deventer station.

For contractor Hegeman- Beton en Industriebouw Nijverdal, we placed 268 metres of steel sheet piling with lengths varying from 7.5 to 10.5 metres. The location of the pit in an urban area required for the vibration-free implementation of the sheet piles. This was done by statically pressing the piles into the ground. It was a complex endeavour because of the busy environment around Deventer station and the contractors’ wish of impeding traffic as less as possible.

The sheet-piling construction was connected to the existing bicycle garage and remains in the ground. It became part of the garage. The work was executed using declutching detectors. Sterk was also responsible for the strut / bracing frame and anchoring of the sheet piling.

Once finished the underground bicycle garage will have space to stall no less than 3600 bicycles for free.

Project details

  • Client: Hegeman Beton- en Industriebouw Nijverdasl
  • Location: Deventer
  • Contract value: € 250.000 - 1.000.000
  • Start date: 19-05-2014
  • End date: 19-12-2015

Used techniques

Anchoring constructions, Construction work, Static driving, Strutting

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Hegeman Beton- en Industriebouw Nijverdasl

Locatie

Deventer

Contractwaarde

€ 250.000 - 1.000.000

Start datum

19-05-2014

Eind datum

19-12-2015

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.

Sterk - Combiwand Neherkade Den Haag

Reconstruction of the Neherkade

Description

The Neherkade in The Hague is currently undergoing a dramatic transformation. As part of this, Sterk has made a long combined wall for the widening of the quay/shore. We also made a cofferdam as well as several sheet pile screens that are part of an underpass for traffic. The removal of the old quay wall is also done by Sterk.

The quay is being widened to make space for extra and re-designed intersections. The new wall consists of a large combined wall that, due to accessibility, was installed from the water using Sterk’s own coupling pontoons. The transportation of the steel tubes was also done via water.

At the intersection “Leeghwaterplein / Slachthuisstraat” a 160 metre long underpass is being created. This will guide the traffic underneath the crossing tram tracks greatly improving traffic flow. As part of this construction we created a cofferdam and several sheet pile screens.

When the combined wall was put into place, a bracing frame was placed after which the excavation could start. The underpass structure was created on site and later was carefully put into place. The space between the underpass walls and the combined walls was filled.

The completion of the project is planned for the end of 2015.

You can watch a short video of Sterk placing the sheet piling for in between the steel tubular piles below.

Project details

  • Client: Combinatie Reconstructie Neherkade Besix/Dura Vermeer
  • Location: Den Haag
  • Contract value: € 250.000 - 1.000.000
  • Start date: 11-04-2014
  • End date: 13-02-2015

Used techniques

Combi sheet pile walls, High-frequency vibration/extraction, In-water work, Tubular post driving
Sterk - Combiwand Neherkade Den Haag

Omschrijving

Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

Lees meer

Opdrachtgever

Combinatie Reconstructie Neherkade Besix/Dura Vermeer

Locatie

Den Haag

Contractwaarde

€ 250.000 - 1.000.000

Start datum

11-04-2014

Eind datum

13-02-2015

Nieuwe brug over het Van Harinxmakanaal
Voor de realisering van de nieuwe brug over het Van Harinxmakanaal in het Friese Dronryp kwamen alle expertises van Sterk zo ongeveer samen. Damwanden, buis- en heipalen, waterwerk, (prefab) constructiewerk en verankering: het kwam allemaal aan bod.

Vervanging van de 75 jaar oude brug over het kanaal was al langere tijd noodzakelijk vanwege de slechte staat waarin die verkeerde. Verkeer met een totaalgewicht van 30 ton of meer mocht er sinds 2014 al niet meer overheen en vanwege veiligheidsaspecten was bediening bij windkracht zes of meer ook niet toegestaan.

440 meter aan stalen damwand
In opdracht van Oosterhof Holman tekende Sterk voor vernieuwing van de verouderde oeverbeschoeiing en bracht het vanaf een ponton op het water met een hydraulische kraan ongeveer 440 meter aan stalen damwand aan. De constructie is verstevigd met meer dan honderd klapankers en 440 meter ankergording, wat ook het nodige constructie- en laswerk op locatie met zich meebracht.

Ook plaatsten we vanaf een ponton op het water de betonpalen die dienen als fundering van de middenpijler van de brug. Daarnaast plaatste Sterk – eveneens vanaf het water – buispalen voor het remming- en geleidewerk en stalen damwand ten behoeve van de bouwkuipen voor de landhoofden.

Het gereedmaken van de buizen voor het remming- en geleidewerk was een uitdagende klus. Met een mal zijn de geplaatste buizen op locatie eerst in de juiste vorm gesneden. Zo kon de horizontale buis, die dient als verbinding tussen de verticale buizen, mooi sluitend worden geplaatst. Aansluitend zijn platen in de buizen gelast om ze te verstevigen en werden de buizen aan de bovenkant dichtgelast.

Het remmingwerk zelf is volledig prefab gemaakt in de lashal van Sterk Metaal in Drachten. De immense gevaartes zijn aansluitend begin juni met een ponton richting de projectlocatie vervoerd. Daar is het op de juiste plek gezet door Sterk, dat ook het hijswerk en afmonteren voor zijn rekening nam. Het vormde het slotakkoord van een project waarin Sterk zijn multidisciplinaire expertise in alle opzichten kon tonen.